Dept. of Trans. PROGRESS Serial No. Contract No. 14-324-07-05 04-3E5004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 100% 04-SOL-80-1.1/R43.5 Federal Project: 04-SOL-113-R22.1/R22.1 NONE Progress payment No. 05 Payment period ending: 11-20-14 MYERS AND SONS CONSTRUCTION LP 4600 NORTHGATE BLVD, STE #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 609,178.90 10,220.00 2.a. Extra Work 4,093.17 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 613,272.07 10,220.00 5. Mobilization 70,000.00 0.00 6. Total Work Completed 683,272.07 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 683,272.07 10,220.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,220.00