Dept. of Trans. FINAL Serial No. Contract No. 15-027-13-55 04-3E5204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-NAP-128-5.1 Federal Project: NONE Progress payment No. 06 Payment period ending: 10-29-14 VALENTINE COPORATION 111 PELICAN WAY SAN RAFAEL, CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 496,934.59 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 496,934.59 0.00 5. Mobilization 6. Total Work Completed 496,934.59 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 496,934.59 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00