Dept. of Trans. PROGRESS Serial No. Contract No. 13-324-07-04 04-3E8204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 70% 04-SON-121-R7.3/11.6 Federal Project: NONE Progress payment No. 02 Payment period ending: 11-20-13 FONSECA/MCELROY GRINDING CO INC 336 E GISH ROAD SAN JOSE CA 95112 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,099,334.33 93,636.10 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,099,334.33 93,636.10 5. Mobilization 35,500.00 0.00 6. Total Work Completed 1,134,834.33 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,134,834.33 93,636.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 93,636.10