Dept. of Trans. PROGRESS Serial No. Contract No. 12-074-09-25 04-3G0104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 39% 87% 04-SM-35-3.8 Federal Project: NONE Progress payment No. 03 Payment period ending: 03-13-12 GRANITE ROCK COMPANY, D.B.A PAVEX CONSTRUCTION 120 GRANITEROCK WAY SAN JOSE, CA 95136 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,670.00 0.00 2.a. Extra Work 813,111.56 114,562.87 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 818,781.56 114,562.87 5. Mobilization 6. Total Work Completed 818,781.56 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 818,781.56 114,562.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 114,562.87