Dept. of Trans. PROGRESS Serial No. Contract No. 14-143-13-27 04-3G0204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 11% 04-SM-35-13.1/13.1 Federal Project: STP-S035(8) Progress payment No. 01 Payment period ending: 05-20-14 PAVEX CONSTRUCTION DIVISION 120 GRANITE ROCK WAY SAN JOSE CA 95136 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 164,618.00 164,618.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 34,585.00 34,585.00 4. Earned Subject to Retention 199,203.00 199,203.00 5. Mobilization 7,980.00 7,980.00 6. Total Work Completed 172,598.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 207,183.00 207,183.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 207,183.00