Dept. of Trans. PROGRESS Serial No. Contract No. 18-053-12-04 04-3G0804 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 91% Location: Federal Project: 04-SON-1-30.5 ACNH-P001(618) Progress payment No. 010 Payment period ending: 02-20-18 GRANITE CONSTRUCTION COMPANY 1324 SOUTH STATE ST UKIAH CA 95482 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,678,354.62 17,742.50 2. a. Extra Work 51,701.75 27,824.75 b. Adustment Comp. 5,402.40 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,735,458.77 45,567.25 5. Mobilization 354,800.00 0.00 6. Total Work Completed 4,090,258.77 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,090,258.77 45,567.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 45,567.25