Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 17-207-09-31 04-3G1104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-SON-116-39.0/40.0 STP-P116(47) Progress payment No. 006 Payment period ending: 03-20-17 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 359,548.00 0.00 2. a. Extra Work 134,430.42 42,258.92 b. Adustment Comp. 25,455.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 519,433.42 42,258.92 5. Mobilization 50,000.00 0.00 6. Total Work Completed 569,433.42 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 569,433.42 42,258.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 42,258.92