Dept. of Trans. PROGRESS Serial No. Contract No. 16-049-11-59 04-3G1704 PROGRESS PAYMENT VOUCHER %complete: %time: 52% 43% Location: Federal Project: 04-SF-101-3.4 NHP-Q101(271) Progress payment No. 002 Payment period ending: 02-20-16 PACIFIC INFRASTRUCTURE CONSTRUCTION LLC 871 COTTING CT #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 331,490.20 249,185.20 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -55,379.16 4. Earned Subject to Retention 331,490.20 193,806.04 5. Mobilization 76,000.00 16,000.00 6. Total Work Completed 407,490.20 7. Deductions -1,641.12 -345.50 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 405,849.08 209,460.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 209,460.54