Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 19-353-14-07 04-3G3054 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-SM-92-15.3/15.5 NONE 04-ALA-92-R0.0/R1.6 04-SF-80-R5.5/R8.8 Progress payment No. 018 Payment period ending: 12-09-19 BLEYCO INCORPORATED 11425 CULL CANYON RD CASTRO VALLEY CA 94552 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,405,923.00 0.00 2. a. Extra Work 318,095.77 61,807.94 b. Adustment Comp. 199,500.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,923,518.77 61,807.94 5. Mobilization 340,000.00 0.00 6. Total Work Completed 4,263,518.77 7. Deductions -32,000.00 -32,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,231,518.77 29,807.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 29,807.94