Dept. of Trans. PROGRESS Serial No. Contract No. 15-112-10-04 04-3G4434 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 44% Location: Federal Project: 04-SF-80-5.8/7.8 NONE Progress payment No. 003 Payment period ending: 04-20-15 GOLDEN STATE BRIDGE, INC. 3701 MALLARD DRIVE BENICIA, CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 59,888.50 55,838.50 2. a. Extra Work b. Adustment Comp. 4,617.03 0.00 3. Materials on Hand 4. Earned Subject to Retention 64,505.53 55,838.50 5. Mobilization 62,500.00 62,500.00 6. Total Work Completed 127,005.53 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 127,005.53 118,338.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 118,338.50