Dept. of Trans. PROGRESS Serial No. Contract No. 25-078-16-34 04-3G4444 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 52% Location: Federal Project: 04-SF-80-5.7/7.5 NONE Progress payment No. 013 Payment period ending: 03-20-25 AMERICAN BRIDGE COMPANY 1000 AMERICAN BRIDGE WAY CORAOPOLIS PA 15108 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,074,053.89 1,620,261.17 2. a. Extra Work 328,197.14 141,188.21 b. Adustment Comp. 3. Materials on Hand 1,208,302.82 -219,675.61 4. Earned Subject to Retention 9,610,553.85 1,541,773.77 5. Mobilization 1,881,000.00 0.00 6. Total Work Completed 10,283,251.03 7. Deductions -14,450.64 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,477,103.21 1,541,773.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,541,773.77