Dept. of Trans. PROGRESS Serial No. Contract No. 25-107-14-56 04-3G4444 PROGRESS PAYMENT VOUCHER %complete: %time: 61% 63% Location: Federal Project: 04-SF-80-5.7/7.5 NONE Progress payment No. 014 Payment period ending: 04-20-25 AMERICAN BRIDGE COMPANY 1000 AMERICAN BRIDGE WAY CORAOPOLIS PA 15108 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,088,807.89 2,014,754.00 2. a. Extra Work 360,637.14 32,440.00 b. Adustment Comp. 3. Materials on Hand 903,000.00 -305,302.82 4. Earned Subject to Retention 11,352,445.03 1,741,891.18 5. Mobilization 1,980,000.00 99,000.00 6. Total Work Completed 12,429,445.03 7. Deductions -15,211.20 -760.56 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,317,233.83 1,840,130.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,840,130.62