Dept. of Trans. PROGRESS Serial No. Contract No. 25-167-12-49 04-3G4444 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 87% Location: Federal Project: 04-SF-80-5.7/7.5 NONE Progress payment No. 016 Payment period ending: 06-20-25 AMERICAN BRIDGE COMPANY 1000 AMERICAN BRIDGE WAY CORAOPOLIS PA 15108 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,848,608.13 2,071,506.27 2. a. Extra Work 510,476.79 49,554.68 b. Adustment Comp. 3. Materials on Hand 738,000.00 -165,000.00 4. Earned Subject to Retention 15,097,084.92 1,956,060.95 5. Mobilization 1,980,000.00 0.00 6. Total Work Completed 16,339,084.92 7. Deductions -15,211.20 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,061,873.72 1,956,060.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,956,060.95