Dept. of Trans. PROGRESS Serial No. Contract No. 21-294-13-05 04-3G4544 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 49% Location: Federal Project: 04-SM-92-R14.4/R18.8 NONE 04-ALA-92-R0.0/R2.4 Progress payment No. 019 Payment period ending: 10-20-21 GOLDEN STATE BRIDGE INC 3701 MALLARD DR BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,493,837.19 -148,000.00 2. a. Extra Work 3,455,493.48 696,563.11 b. Adustment Comp. 1,963,675.00 613,277.00 3. Materials on Hand 4. Earned Subject to Retention 12,913,005.67 1,161,840.11 5. Mobilization 1,400,000.00 0.00 6. Total Work Completed 14,313,005.67 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,313,005.67 1,161,840.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,161,840.11