Dept. of Trans. PROGRESS Serial No. Contract No. 21-197-13-17 04-3G4744 PROGRESS PAYMENT VOUCHER %complete: %time: 12% 13% Location: Federal Project: 04-CC-580-6.1/7.7 NONE 04-MRN-580-0.0/2.7 Progress payment No. 004 Payment period ending: 07-20-21 ALLIED PAINTING INC 4 LARWIN RD CHERRY HILL NJ 08034 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,643,420.00 2,239,670.00 2. a. Extra Work 10,472.77 3,549.73 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,653,892.77 2,243,219.73 5. Mobilization 1,925,000.00 1,540,000.00 6. Total Work Completed 4,578,892.77 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,578,892.77 3,783,219.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,783,219.73