Dept. of Trans. FINAL Serial No. Contract No. 13-137-07-15 04-3G5604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SM-35-28.9 Federal Project: NONE Progress payment No. 07 Payment period ending: 04-16-12 REDWOOD ENGINEERING CONSTRUCTION 2336 EL CAMINO REAL REDWOOD CITY, CA 94063 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,975.00 3,975.00 2.a. Extra Work 644,997.98 152,026.96 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 648,972.98 156,001.96 5. Mobilization 6. Total Work Completed 648,972.98 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 648,972.98 156,001.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 156,001.96