Dept. of Trans. PROGRESS Serial No. Contract No. 21-201-15-31 04-3G6204 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 100% Location: Federal Project: 04-SF-101-1.5/2.0 ACNH-Q101(366) Progress payment No. 016 Payment period ending: 07-20-21 MYERS & SONS CONSTRUCTION LLC 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,591,255.89 284,584.75 2. a. Extra Work 6,792,398.83 34,020.80 b. Adustment Comp. 10,440,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 32,823,654.72 318,605.55 5. Mobilization 1,900,000.00 0.00 6. Total Work Completed 34,723,654.72 7. Deductions -25,035.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 34,698,619.72 318,605.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 318,605.55