Dept. of Trans. PROGRESS Serial No. Contract No. 24-109-15-45 04-3G6304 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 20% Location: Federal Project: 04-SCL-9-4.9/4.9 NONE Progress payment No. 013 Payment period ending: 04-20-24 MYERS & SONS CONSTRUCTION LLC 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,856,460.75 365,677.34 2. a. Extra Work 376,070.45 100,439.14 b. Adustment Comp. 595,606.44 0.00 3. Materials on Hand 4. Earned Subject to Retention 10,828,137.64 466,116.48 5. Mobilization 1,195,261.80 0.00 6. Total Work Completed 12,023,399.44 7. Deductions -2,669.33 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,020,730.11 466,116.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 466,116.48