Dept. of Trans. PROGRESS Serial No. Contract No. 18-169-16-22 04-3G6414 PROGRESS PAYMENT VOUCHER %complete: %time: 61% 31% Location: Federal Project: 04-NAP-29-37.0 ACST-P029(128) Progress payment No. 014 Payment period ending: 06-20-18 VALENTINE CORPORATION 111 PELICAN WAY SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,934,653.50 190,259.25 2. a. Extra Work 428,786.37 40,353.93 b. Adustment Comp. 3. Materials on Hand 13,490.26 -37,009.00 4. Earned Subject to Retention 3,376,930.13 193,604.18 5. Mobilization 239,000.00 0.00 6. Total Work Completed 3,602,439.87 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,615,930.13 193,604.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 193,604.18