Dept. of Trans. SEMI-FINAL Serial No. Contract No. 17-297-10-56 04-3G6504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-SOL-680-0.0/13.1 NHPI-680-1(73) Progress payment No. 013 Payment period ending: 12-18-15 DESILVA GATES CONSTRUCTION LP PO BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,113,260.10 0.00 2. a. Extra Work 1,628,570.18 12,064.42 b. Adustment Comp. -921,593.86 39,452.88 3. Materials on Hand 4. Earned Subject to Retention 10,820,236.42 51,517.30 5. Mobilization 1,275,000.00 0.00 6. Total Work Completed 12,095,236.42 7. Deductions -12,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,083,236.42 51,517.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 51,517.30