Dept. of Trans. PROGRESS Serial No. Contract No. 19-294-16-16 04-3G6904 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 97% Location: Federal Project: 04-SOL-80-13.9/13.9 BHIM-080-2(370) Progress payment No. 004 Payment period ending: 10-20-19 BRIDGEWAY CIVIL CONSTRUCTORS INC 4950 ALLISON PKWY #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 993,760.80 365,593.80 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -5,950.62 4. Earned Subject to Retention 993,760.80 359,643.18 5. Mobilization 234,650.00 0.00 6. Total Work Completed 1,228,410.80 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,228,410.80 359,643.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 359,643.18