Dept. of Trans. PROGRESS Serial No. Contract No. 16-078-10-59 04-3G7004 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 0% Location: Federal Project: 04-SF-101-1.6/4.1 NHP-000C(412) 04-SF-280-R3.7/R6.7 04-MRN-101-7.6/17.8 Progress payment No. 001 Payment period ending: 03-20-16 GHILOTTI BROS INC 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,892.80 27,892.80 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 27,892.80 27,892.80 5. Mobilization 6. Total Work Completed 27,892.80 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 27,892.80 27,892.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 27,892.80