Dept. of Trans. PROGRESS Serial No. Contract No. 24-165-11-15 04-3G9004 PROGRESS PAYMENT VOUCHER %complete: %time: 16% 6% Location: Federal Project: 04-SON-116-46.5/46.8 CSTG-X097(44) 04-SON-121-6.6/R7.0 Progress payment No. 005 Payment period ending: 06-20-24 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 896,077.64 390,636.00 2. a. Extra Work 65,633.98 1,588.21 b. Adustment Comp. 3. Materials on Hand 183,154.00 141,191.00 4. Earned Subject to Retention 1,144,865.62 533,415.21 5. Mobilization 709,500.00 236,500.00 6. Total Work Completed 1,671,211.62 7. Deductions -2,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,852,365.62 769,915.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 769,915.21