Dept. of Trans. PROGRESS Serial No. Contract No. 15-273-15-52 04-3J0004 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 100% Location: Federal Project: 04-NAP-121-0.0/11.6 NONE Progress payment No. 007 Payment period ending: 09-29-15 OC JONES & SONS, INC 1520 FOURTH STREET BERKELEY, CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 613,050.72 15,766.88 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 613,050.72 15,766.88 5. Mobilization 6. Total Work Completed 613,050.72 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 613,050.72 15,766.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 15,766.88