Dept. of Trans. PROGRESS Serial No. Contract No. 15-093-07-56 04-3J0104 PROGRESS PAYMENT VOUCHER %complete: %time: 29% 60% Location: Federal Project: 04-NAP-29-0.0/3.1 NONE Progress payment No. 004 Payment period ending: 01-05-15 DISNEY CONSTRUCTION 859 COWAN ROAD, SUITE 3 BURLINGAME, CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 775,908.48 88,745.74 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 775,908.48 88,745.74 5. Mobilization 6. Total Work Completed 775,908.48 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 775,908.48 88,745.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 88,745.74