Dept. of Trans. FINAL Serial No. Contract No. 25-225-11-09 04-3J0704 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-CC-80-10.1/13.5 ACIM-801(997) Progress payment No. 018 Payment period ending: 01-24-25 FBD VANGUARD CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,470,258.93 0.00 2. a. Extra Work 22,754,307.42 10,360.74 b. Adustment Comp. 5,912,444.43 0.00 3. Materials on Hand 4. Earned Subject to Retention 44,137,010.78 10,360.74 5. Mobilization 4,000,000.00 0.00 6. Total Work Completed 48,137,010.78 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 48,137,010.78 10,360.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,360.74