Dept. of Trans. PROGRESS Serial No. Contract No. 22-112-17-21 04-3J1304 PROGRESS PAYMENT VOUCHER %complete: %time: 15% 37% Location: Federal Project: 04-ALA-580 SIMG-X001(665) Progress payment No. 002 Payment period ending: 04-20-22 PTM GENERAL ENGINEERING SERVICES INC PO BOX 7745 RIVERSIDE CA 92513 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 221,104.55 28,500.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 221,104.55 28,500.00 5. Mobilization 105,000.00 35,000.00 6. Total Work Completed 326,104.55 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions 0.00 19,260.46 c. Reduction after 95% Comp. 9. Total pay to Contractor 326,104.55 82,760.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 82,760.46