Dept. of Trans. PROGRESS Serial No. Contract No. 21-263-13-35 04-3J3204 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 58% Location: Federal Project: 04-SCL-280-11.5/R20.6 ACNH-280-1(150) Progress payment No. 018 Payment period ending: 09-20-21 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 39,345,251.31 264,687.45 2. a. Extra Work 820,289.36 21,960.54 b. Adustment Comp. -534,590.96 0.00 3. Materials on Hand 4. Earned Subject to Retention 39,630,949.71 286,647.99 5. Mobilization 3,365,000.00 0.00 6. Total Work Completed 42,995,949.71 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 42,995,949.71 286,647.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 286,647.99