Dept. of Trans. PROGRESS Serial No. Contract No. 17-352-10-46 04-3J4304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 57% Location: Federal Project: 04-SM-280-10.8/10.8 NONE Progress payment No. 002 Payment period ending: 12-20-17 NORCAL GENERAL CONSTRUCTION CORP 1950 MAJESTIC CT SAN JOSE CA 95132 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 621,645.00 62,510.00 2. a. Extra Work 160,880.55 17,937.52 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 782,525.55 80,447.52 5. Mobilization 25,000.00 0.00 6. Total Work Completed 807,525.55 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 807,525.55 80,447.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 80,447.52