Dept. of Trans. PROGRESS Serial No. Contract No. 18-355-14-40 04-3J5704 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 62% Location: Federal Project: 04-ALA-80-5.8 NONE Progress payment No. 003 Payment period ending: 11-09-18 FBD VANGUARD CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 492,762.35 31,695.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 492,762.35 31,695.50 5. Mobilization 6. Total Work Completed 492,762.35 7. Deductions -23,644.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 469,118.35 31,695.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 31,695.50