Dept. of Trans. PROGRESS Serial No. Contract No. 21-232-10-35 04-3J7104 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 88% Location: Federal Project: 04-SCL-280-11.3/11.3 HSIM-2801(151) Progress payment No. 004 Payment period ending: 08-20-21 GRANITE ROCK COMPANY PO BOX 50001 WATSONVILLE CA 950775001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 201,046.62 0.00 2. a. Extra Work 41,272.39 41,272.39 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 242,319.01 41,272.39 5. Mobilization 22,000.00 0.00 6. Total Work Completed 264,319.01 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 264,319.01 41,272.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 41,272.39