Dept. of Trans. PROGRESS Serial No. Contract No. 22-048-09-56 04-3K3104 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 1% Location: Federal Project: 04-ALA-13 B1NH-X001(645) Progress payment No. 001 Payment period ending: 02-20-22 ST FRANCIS ELECTRIC INC 975 CARDEN ST SAN LEANDRO CA 94577 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,250.00 1,250.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 429,869.09 429,869.09 4. Earned Subject to Retention 431,119.09 431,119.09 5. Mobilization 114,000.00 114,000.00 6. Total Work Completed 115,250.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 545,119.09 545,119.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 545,119.09