Dept. of Trans. PROGRESS Serial No. Contract No. 21-326-15-14 04-3K3304 PROGRESS PAYMENT VOUCHER %complete: %time: 3% 58% Location: Federal Project: 04-SCL-17-5.1/13.3 B1NH-X085(61) 04-SCL-85-R18.0/R18.0 04-SCL-87-7.5/7.5 Progress payment No. 003 Payment period ending: 11-20-21 ST FRANCIS ELECTRIC INC 975 CARDEN ST SAN LEANDRO CA 94577 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,922.00 0.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 666,611.89 666,611.89 4. Earned Subject to Retention 678,533.89 666,611.89 5. Mobilization 105,000.00 105,000.00 6. Total Work Completed 116,922.00 7. Deductions -105,000.00 -105,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 678,533.89 666,611.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 666,611.89