Dept. of Trans. PROGRESS Serial No. Contract No. 17-181-09-04 04-3K3804 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 83% Location: Federal Project: 04-SCL-680-1.7/1.7 NONE Progress payment No. 002 Payment period ending: 06-30-17 PIPE AND PLANT SOLUTIONS INC 225 3RD ST OAKLAND CA 94607 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 370,797.05 234,327.19 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 370,797.05 234,327.19 5. Mobilization 6. Total Work Completed 370,797.05 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 370,797.05 234,327.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 234,327.19