Dept. of Trans. PROGRESS Serial No. Contract No. 24-017-17-36 04-3K4204 PROGRESS PAYMENT VOUCHER %complete: %time: 35% 69% Location: Federal Project: 04-SF-35-1.3/1.3 SNHG-P035(13) Progress payment No. 004 Payment period ending: 01-20-24 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 424,989.50 135,225.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 161,292.00 161,292.00 4. Earned Subject to Retention 586,281.50 296,517.00 5. Mobilization 165,300.00 34,800.00 6. Total Work Completed 590,289.50 7. Deductions -6,941.41 -1,461.35 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 744,640.09 329,855.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 329,855.65