Dept. of Trans. PROGRESS Serial No. Contract No. 19-311-09-11 04-3Q1604 PROGRESS PAYMENT VOUCHER %complete: %time: 61% 100% Location: Federal Project: 04-ALA-880-30.4/30.6 NONE Progress payment No. 003 Payment period ending: 10-25-19 CALIFORNIA ENGINEERING CONTRACTORS,INC 20 HAPPY VALLEY RD PLEASANTON CA 94566 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 869,866.96 413,988.09 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 869,866.96 413,988.09 5. Mobilization 6. Total Work Completed 869,866.96 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions 0.00 34,869.61 c. Reduction after 95% Comp. 9. Total pay to Contractor 869,866.96 448,857.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 448,857.70