Dept. of Trans. PROGRESS Serial No. Contract No. 24-108-16-58 04-3Q5704 PROGRESS PAYMENT VOUCHER %complete: %time: 68% 44% Location: Federal Project: 04-VAR-101-1.1/4.1 NONE Progress payment No. 006 Payment period ending: 04-20-24 DISNEY CONSTRUCTION INC 533 AIRPORT BLVD #120 BURLINGAME CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,556,502.00 905,434.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 38,759.58 -88,831.96 4. Earned Subject to Retention 2,595,261.58 816,602.04 5. Mobilization 430,000.00 21,500.00 6. Total Work Completed 2,986,502.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,025,261.58 838,102.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 838,102.04