Dept. of Trans. PROGRESS Serial No. Contract No. 21-053-09-28 04-3Q8304 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 28% Location: Federal Project: 04-SCL-87-5.2/5.2 NONE Progress payment No. 005 Payment period ending: 02-20-21 CONSTRUCTION H INC 2421 LINCOLN AVE RICHMOND CA 94804 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 573,721.00 81,921.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 573,721.00 81,921.00 5. Mobilization 6. Total Work Completed 573,721.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 573,721.00 81,921.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 81,921.00