Dept. of Trans. PROGRESS Serial No. Contract No. 09-085-08-50 04-3S6004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 99% 04-NAP-29-38.8/38.8 Federal Project: 04-NAP-29-42.6/42.6 ER-43F9(4) Progress payment No. 03 Payment period ending: 03-20-09 AMCO BUILDERS 3116 INDUSTRIAL BLVD WEST SACRAMENTO CA 95691 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 64,323.54 -14,628.75 2.a. Extra Work 15,801.93 15,801.93 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 80,125.47 1,173.18 5. Mobilization 6. Total Work Completed 80,125.47 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 75,125.47 1,173.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,173.18