Dept. of Trans. PROGRESS Serial No. Contract No. 09-264-09-27 04-3S6724 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 16% 46% 04-SM-84-13.8/13.8 Federal Project: 04-SM-84-16.4/16.4 ER-43I4(4) Progress payment No. 01 Payment period ending: 09-20-09 A I S CONSTRUCTION COMPANY 6420 VIA REAL SUITE 6 CARPINTERIA CA 93013 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 45,550.34 45,550.34 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 45,550.34 45,550.34 5. Mobilization 9,375.00 9,375.00 6. Total Work Completed 54,925.34 7. Deductions -2,900.00 -2,900.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 52,025.34 52,025.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 52,025.34