Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 09-344-08-29 04-3S7704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SON-116-4.5/4.5 Federal Project: ER-43F6(4) Progress payment No. 05 Payment period ending: 11-10-09 AMLAND CORP 3168 KNIGHTS BRIDGE ROAD SAN JOSE CA 95132 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 604,281.30 85,418.70 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 604,281.30 85,418.70 5. Mobilization 70,000.00 0.00 6. Total Work Completed 674,281.30 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. 0.00 30,753.66 c. Reduction after 95% Comp. 9. Total pay to Contractor 664,281.30 106,172.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 106,172.36