Dept. of Trans. PROGRESS Serial No. Contract No. 09-054-09-03 04-3S8404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 54% 16% 04-SON-1-26.6/26.7 Federal Project: ER-43GO(4) Progress payment No. 04 Payment period ending: 02-20-09 GORDON N BALL INC 333 CAMILLE AVENUE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 887,132.50 226,669.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 18,279.92 18,279.92 4. Earned Subject to Retention 905,412.42 244,948.92 5. Mobilization 180,500.00 0.00 6. Total Work Completed 1,067,632.50 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,085,912.42 244,948.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 244,948.92