Dept. of Trans. PROGRESS Serial No. Contract No. 09-164-14-33 04-3S8404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 55% 04-SON-1-26.6/26.7 Federal Project: ER-43GO(4) Progress payment No. 08 Payment period ending: 06-20-09 GORDON N BALL INC 333 CAMILLE AVENUE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,522,785.50 146,500.00 2.a. Extra Work 4,822.11 0.00 b. Adjustment Comp. -10,000.00 0.00 3. Materials on Hand 0.00 -42,773.00 4. Earned Subject to Retention 1,517,607.61 103,727.00 5. Mobilization 190,000.00 0.00 6. Total Work Completed 1,707,607.61 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,707,607.61 103,727.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 103,727.00