Dept. of Trans. PROGRESS Serial No. Contract No. 21-344-11-17 04-3W8404 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 50% Location: Federal Project: 04-SCL-152-10.1/10.4 NONE Progress payment No. 003 Payment period ending: 12-10-21 ABSL CONSTRUCTION 29393 PACIFIC ST HAYWARD CA 94544-6018 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 543,232.95 262,573.62 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 543,232.95 262,573.62 5. Mobilization 6. Total Work Completed 543,232.95 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 543,232.95 262,573.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 262,573.62