Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 23-250-14-27 04-3Y1004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-SOL-84-12.5/12.5 NONE Progress payment No. 003 Payment period ending: 04-05-23 WEBER GENERAL ENGINEERING INC 240 WEST E ST DIXON CA 95620 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,483.20 0.00 2. a. Extra Work 49,199.71 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 50,682.91 0.00 5. Mobilization 6. Total Work Completed 50,682.91 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 50,682.91 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00