Dept. of Trans. FINAL Serial No. Contract No. 26-015-13-32 04-3Y1304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-ALA-580-43.1/43.1 NONE Progress payment No. 009 Payment period ending: 10-30-25 REDGWICK CONSTRUCTION CO. 21 HEGENBERGER CT OAKLAND CA 94621 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,578.00 0.00 2. a. Extra Work 1,167,295.20 -10,890.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,174,873.20 -10,890.00 5. Mobilization 6. Total Work Completed 1,174,873.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,174,873.20 -10,890.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -10,890.00