Dept. of Trans. PROGRESS Serial No. Contract No. 24-137-10-53 04-3Y1804 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 100% Location: Federal Project: 04-VAR-4-18.6/18.6 NONE Progress payment No. 004 Payment period ending: 05-17-24 ST FRANCIS ELECTRIC LLC 975 CARDEN ST SAN LEANDRO CA 94577 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 105,033.75 21,936.17 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 105,033.75 21,936.17 5. Mobilization 6. Total Work Completed 105,033.75 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 105,033.75 21,936.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 21,936.17