Dept. of Trans. PROGRESS Serial No. Contract No. 23-200-14-56 04-3Y5104 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 75% Location: Federal Project: 04-ALA-880-8.4/8.7 NONE Progress payment No. 002 Payment period ending: 07-20-23 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 462,445.91 188,996.64 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 462,445.91 188,996.64 5. Mobilization 6. Total Work Completed 462,445.91 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 462,445.91 188,996.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 188,996.64