Dept. of Trans. PROGRESS Serial No. Contract No. 23-167-13-14 04-3Y5504 PROGRESS PAYMENT VOUCHER %complete: %time: 28% 59% Location: Federal Project: 04-ALA-580-4.7/4.8 NONE Progress payment No. 001 Payment period ending: 06-09-23 VIKING CONSTRUCTION CO INC 11315 SUNRISE GOLD CIR #A RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 784,727.66 784,727.66 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 784,727.66 784,727.66 5. Mobilization 6. Total Work Completed 784,727.66 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 784,727.66 784,727.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 784,727.66