Dept. of Trans. PROGRESS Serial No. Contract No. 24-023-16-23 04-3Y6704 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 55% Location: Federal Project: 04-SCL-130-17.9/17.9 NONE Progress payment No. 003 Payment period ending: 01-09-24 MYERS & SONS CONSTRUCTION LLC 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 558,199.88 345,381.91 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 558,199.88 345,381.91 5. Mobilization 6. Total Work Completed 558,199.88 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 558,199.88 345,381.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 345,381.91